Coal handling
Jetty-fed receiving conveyor into the coal yard and coal mill, adjacent to the main power block.
H&WBAsia PacificEnergy FrontierTwo approximately 350 MW supercritical pulverized coal boiler units planned for Camarines Norte, Philippines.
The project is planned as an approximately 700 MW facility comprising two approximately 350 MW supercritical PCB units at Barangay Osmeña, Jose Panganiban.
It is intended to augment supply in the Luzon grid, support network reliability and contribute to economic development in Camarines Norte.

Drone and ground surveys of the approximately 50-hectare site at Sitio Kalibigaho, Barangay Osmeña, confirming boundaries, terrain and coastal access ahead of construction.




The approximately 700 MW facility is organised around a central power block, coal yard, water treatment area and jetty, with separation between operational and administrative zones.

Jetty-fed receiving conveyor into the coal yard and coal mill, adjacent to the main power block.
Boiler, turbine-generator, condenser and switchyard arranged along the central spine of the site.
Water treatment facility, ash disposal, warehouse and staff housing positioned around the perimeter.
ECC, System Impact Study updates, local endorsements and required approvals.
Interconnection arrangements, EPC strategy and commercial procurement.
FIDIC-based EPC execution, HSSE oversight and delivery controls.
Testing, operations readiness and target commercial operation by 2035.
DOE clearance to undertake grid impact study and start of EIA activities.
Public scoping completed in Jose Panganiban.
NGCP approved the System Impact Study final report.
DOE acknowledgement confirmed the project is not covered by the 2020 Coal Moratorium.